In an appeal of that approval to the Maine Supreme Judicial Court, NextEra Energy Resources accused the commission of ignoring state law requiring a third-party review of alternatives to Central Maine Power’s transmission line. NextEra also said the panel failed to follow the law in determining a public need for the $1 billion project.